This is with regard to the RNA Viva project at Mira Road. I had booked a flat around 1 year back on a higher floor, however since paying the booking amount the builder has not been demanding. They say that they have all the required approvals, and are just awaiting for CC for floors above 11, which is being delayed by the Municipal Corp. Hence flats above 11th floor cannot be registered and hence they are not making demands for further payments.
4 Wings have already been constructed up to the 18th slab, and remaining wings are around 13-15th slabs. No new slabs have been added since november 2012, and before that 1-2 slabs were being added every month.
They also give varied info regd the project, from being a 18 storied tower to 21 storied tower, 9 wings or 8 wings, 3 floor car park to 1 floor car park etc etc & there is no clarity.
Does anyone have any concrete info on the project clearances and as to what is the final decision on the construction ?? What are the final clearances expected ?? Also others facing similar issues here ??
They were earlier quoting possession in Dec 2013, and now are quoting April 2014.
4 Wings have already been constructed up to the 18th slab, and remaining wings are around 13-15th slabs. No new slabs have been added since november 2012, and before that 1-2 slabs were being added every month.
They also give varied info regd the project, from being a 18 storied tower to 21 storied tower, 9 wings or 8 wings, 3 floor car park to 1 floor car park etc etc & there is no clarity.
Does anyone have any concrete info on the project clearances and as to what is the final decision on the construction ?? What are the final clearances expected ?? Also others facing similar issues here ??
They were earlier quoting possession in Dec 2013, and now are quoting April 2014.